A fast, interim dispute resolution process under prompt payment legislation in which an adjudicator decides certain disputes within short timelines, with decisions binding unless set aside or overtaken by a court or arbitration.
Quick
Learn
Professional
In plain terms
Adjudication is a quick 'decide now, argue later if needed' process so payment disputes don't stall projects.
Why it matters
It reshapes dispute strategy: cash flow disputes get decided in weeks, not years.
Practical example
A subcontractor refers a $300,000 unpaid invoice to adjudication and receives a determination within weeks.
Common mistake
Ignoring an adjudication notice, which can lead to an enforceable determination.
Related terms
Authoritative resources
Construction Act, R.S.O. 1990, c. C.30 ↗
Government of Ontario (e-Laws) · Liens, holdback, prompt payment, adjudication and trust provisions, including amendments in force January 1, 2026.
Free
Ontario
Link opened 2026-11-27
Ontario Dispute Adjudication for Construction Contracts ↗
ODACC, the Authority designated under the Construction Act · Adjudicator registry, forms, fees and published guidance on Ontario construction adjudication.
Free
Ontario
Link opened 2026-11-27
Federal Prompt Payment for Construction Work Act, S.C. 2019, c. 29, s. 387 ↗
Justice Laws Website · Prompt payment and adjudication for construction on federal real property; in force December 9, 2023.
Free
Federal
Link opened 2026-11-27
My private note
Verification. Status: Draft, author-researched, not yet professionally reviewed. Content date 2026-11-27. Legal content reflects the law of the jurisdiction named in the entry as researched on that date; always check the current legislation and the executed contract. CCDC wording is not reproduced.